Naples Airport to become first coastal airport in the South with elevated runway, taxiway lighting

Naples Airport's elevated airfield lights, at left, will raise lights 20 inches above ground level, significantly higher than the existing lighting system.
Naples Airport's elevated airfield lights, at left, will raise lights 20 inches above ground level, significantly higher than the existing lighting system.

Naples Airport is working on a first-of-its-kind project to enhance resiliency and post-storm recovery by elevating its lighting system across the airfield.

The Airfield Lighting Rehabilitation and Electrical Vault Replacement Project will include the installation of 1,080 elevated edge lights along the airport’s runways and taxiways.

Watertight lights will be positioned 20 inches off the ground to protect against potential storm surge flooding. The new lights will be LED, which will be brighter and provide energy savings compared to the airfield’s current incandescent lights.

“It's not often that an airport gets to redo the entire airfield. every inch matters when the water is coming up the flood level," said Sandeep Singh, president of AVCON, Inc., an Orlando-based company that provides planning, engineering and construction management needs for airports. "And if we can get a couple of more inches and the lights are further up above the ground, we could prevent damage to the printed circuit board that's in the light.”

Naples Airport will also reconstruct its electrical vault with a storm-resilient design, which includes raising equipment above the base flood elevation and five feet higher than currently situated.

Here’s Chris Rozansky, executive director of the Naples Airport Authority:

"Immediately after Hurricane Ian, we began thinking about what can we do to make this airport more resilient for the future storm events? And it's very challenging because airports need to remain relatively flat for obvious reasons. So we looked at the practical solutions that they use up north. And it's very simple, yet effective. By elevating your light fixtures, you can reduce the risk of storm damage and periods of inoperability."

Elevating airfield lights is a common practice at northern airports so pilots and air traffic controllers maintain visibility during and after snowstorms. However, lights at many airports in the South are mounted flush to the ground or just above ground level, potentially putting them at risk during a flood.

The Naples Airport Authority worked closely with the FAA to advocate for this practical design change for flood-prone airports. As a result, the FAA intends to update its national design standards.

During Hurricane Ian in 2022, portions of Naples Airport were inundated with storm surge, destroying airfield lighting and navigational aids. Storm surge came within inches of flooding the airport’s lighting vault, a breach that potentially could have knocked out all lighting systems and prevented nighttime and low-visibility operations for weeks or even months.

A new elevated airfield lighting system at Naples Airport will include 1,080 edge lights along runways and taxiways.
A new elevated airfield lighting system at Naples Airport will include 1,080 edge lights along runways and taxiways.

The Naples Airport Authority’s Board of Commissioners approved $25.4 million in construction and construction administration services for the Airfield Lighting Rehabilitation and Electrical Vault Replacement Project. Construction funds derive from a combination of insurance proceeds, grants from the Florida Department of Environmental Protection’s Resilient Florida Program, allocations from the FAA’s Infrastructure Investment and Jobs Act (IIJA), Florida Department of Transportation Public Transportation Grant Agreement (PTGA) and capital funds included in the Naples Airport Authority’s annual budget. Naples Airport receives no local taxpayer dollars to fund operations or capital projects.

The airfield lighting project, which was approved in October 2025 and is expected to take 20 months to complete, is Naples Airport’s latest initiative aimed at building resilience. In August 2025, Naples Airport received delivery of its new Tiger Dam flood barrier system, which consists of 3,000 feet of flexible tubing that, when filled with water, forms a strong, airtight harrier. The Tiger Dam system can be deployed within hours to protect buildings, equipment and technology against potential flooding.

WGCU is your trusted source for news and information in Southwest Florida. We are a nonprofit public service, and your support is more critical than ever. Keep public media strong and donate now. Thank you.

Trusted by over 30,000 local subscribers

Local News, Right Sized for Your Morning

Quick briefs when you are busy, deeper explainers when it matters, delivered early morning and curated by WGCU editors.

  • Environment
  • Local politics
  • Health
  • And more

Free and local. No spam. Unsubscribe anytime.

More from WGCU